Roll-down shutter based on a single push button (from softwareversion 1.13.1 onwards)
Situation
This step-by-step guide explains how to program a roll-down shutter based on a single push button.
Starting point
The starting point for this step-by-step guide is a project that already encompasses Project information and for which a plan is already drawn up or uploaded.
Step 1: Add a roll-down shutter
- Click on Creation at the top of the screen.
- Click on add an output.
- Click on roll-down shutter in the list of options on the right hand side of the screen. The icon appears on the plan.
- Drag the roll-down shutter to the correct location and give it a recognisable name.
- Choose an existing location from the list of options or click on add a location if you have not previously defined one.
- Click on modify basic settings to program the run time of the roll-down shutter.
A pop-up window will appear.
- Enter the measured or known run times.
- Click on save to close the pop-up window.
- Click on save to return to the Creation start screen.
- Repeat the steps until all roll-down shutters controlled by the single push button have been added.
- Return to the start screen for Creation.
Step 2: Add a single push button
- Click on add an input.
- Click on single push button in the list of options in the right-hand window. The icon appears on the plan.
- Drag the single push button to the correct location and give it a recognisable name.
- Choose an existing location from the list of options or click on add a location if you have not previously defined one.
- Click on save to return to the Creation start screen.
Step 3: Create a 'Operate roll-down shutters' action
- Click on add an action. The action will appear as a text balloon on the plan.
- Drag the action to a logical and appropriate place, e.g. to the relevant input or output.
- Give the action a name.
- Choose an existing location from the list of options or click on add a location if you have not previously defined one.
- Click on continue to go to the Players tab.
- Click on the roll-down shutters and the single push button on the plan to link them to the action.
- Click on continue to go to the Basic behaviour tab.
- Change the basic behaviour to predefined by clicking on the arrow in the frame of the drop-down list.
- A pop-up window will open.
- Click on OK to close the window.
- Click on continue to go to the Conditions tab.
- Click on continue to go to the Time automation tab.
- Click on save to return to the Creation start screen.
Result
You can now continue with step Cabinet lay-out or step Realisation.