Installation preparation

Switch off the mains.

  • You can install a maximum of 20 Digital blacks in your Niko Home Control installation.
  • Mount the Digital black, 230 V at 110 to 160 cm above floor level. When you use the Digital black, 230 V as a "central control screen" a mounting height of 150 - 160 cm above floor level is recommended.
  • Screw mounting requires vertically aligned screws.
  • You need an L and N wire in the wall mounting box to make this Digital black, 230 V working.

Wiring options

Single-pole switch

  • Connect the Digital black, 230 V as follows in the wall mounting box:
    • Use rigid wiring. Maximum 2 x 1.5mm² or 1 x 2.5mm² per screw terminal.
    • Connect the L and N wire.
    • Connect the wire from the lamp to the L1 terminal.
    • Leave the E1 terminal unconnected if you do not use extension buttons.
  • Check the Wi-Fi network page to prepare the correct data wiring and home router connection.

Single-pole switch with extension buttons 

  • Connect the Digital black, 230 V as follows in the wall mounting box:
    • Use rigid wiring. Maximum 2 x 1.5mm² or 1 x 2.5mm² per screw terminal.
    • Connect the L and N wire.
    • Connect the wire from the lamp to the L1 terminal.
    • Connect the wire(s) from the extension button(s) to the E1 terminal.
  • You can add up to 30 N.O. (Normal Open) classic push buttons (170-00000) on a maximum of 100 m of standard wiring (section: 1.5mm² or 2.5mm²).


    

Installation

Switch off the mains.

  • Apply a stripping length of 6 mm.
  • Use rigid wiring. Maximum 2 x 1.5mm² or 1 x 2.5mm² per screw terminal.

  • Mount the Digital black, 230 V at 110 to 160 cm above floor level. When you use the Digital black, 230 V as a "central control screen" a mounting height of 150 - 160 cm above floor level is recommended.
  • Mount the Digital black in a vertical wall respecting to the TOP-marking.
  • Screw mounting requires vertically aligned screws.
  • Before mounting the display part make sure that you remove the dust protection tape from the base.

Switch on the mains.

  • On the base, there is a small push button to switch the relay ON-OFF when no display is attached. In this way, you can test the switching function during the construction process or apply some construction site lighting without having the risk of damaging the display.
  • The button has a toggle function (push => ON; push again => OFF).

Switch off the mains.

Note: If the Digital black does not click easily onto the mounting bracket, please try the following:

  1. The safety screw at the bottom of the display might be blocking the clicking mechanism. Please verify that the safety screw has been screwed tightly in the UNLOCK position (see step e, but turn the screw in the opposite direction to unlock).
  2. The Digital black might not have been lowered correctly onto the two protruding supports at the top of the mounting bracket (see step d). Please try lowering the Digital black correctly onto the protruding supports. The Digital black should click easily into the mounting bracket. Don’t try to force it or you might damage the connection pins at the back of the Digital black's display.

To avoid theft you can screw in a safety screw on the bottom of the display part. Use an Allen (hex) key of metric 2 mm. To avoid damage do not over tighten the safety screw.